IMSS Milestones
Goals and Milestones:
Done Submit IPv6 over Fibre Channel draft to IESG for consideration as Proposed Standard
RFC 3831
Aug 04   Work with T11.5 to determine what additional MIB modules are needed
Storage Management Routing Information MIB (SM-RTM)
Oct 04   Submit Fibre Channel Domain Manager MIB to IESG for consideration as Proposed Standard
Renamed Fibre Channel Fabric Address Manager MIB
Will be voted on this week by T11.
Oct 04   Submit Fibre Channel Name Server MIB to IESG for consideration as Proposed Standard
Undergoing comment resolution. Should be voted on by next IETF mtg
Jan 05   Submit Extensions for Fibre Channel Interfaces MIB to IESG for consideration as Proposed Standard
On Hold
Jan 05   Review working group charter and determine what additional work, if any, should be undertaken by working group